A Simple Guide To Getting Consent For Mountain Mods In NZ
When setting up a Mountain Mod in New Zealand, there are two key types of consents to consider
Here's a quick overview to help you understand the process, when you need to engage with your local council, and what the incoming legislation means for you.
-
Building consent ensures your Mountain Mod meets the Building Code for safety, durability, and livability.
You need to apply to your local council if:
The Mod will be permanently fixed to the land.
You're connecting it to utilities (e.g., water, power, or sewerage).
It's being used as a full-time home.
Examples of When Building Consent Is Required:
Installing a Mountain Mod as a permanent granny flat with plumbing and electricity.
Using a Mod as a rental unit on your property.
Examples of When Building Consent Is NOT Required:
Using the Mod as a temporary, mobile structure not connected to utilities.
Setting up a Mod for short-term storage or as a workshop without modifications
-
The New Zealand government has introduced a new legislation aimed at making it easier to set up small dwellings like granny flats. This legislation allows certain homes up to 70 m² to be exempt from building consent, provided they meet specific criteria.
Here's what it means:
The Mod must comply with the Building Code, even if consent is not required.
You'll still need to notify the council and get an exemption approval, but the process is faster and cheaper.
These exemptions are intended to reduce red tape, making it easier for homeowners to provide additional housing.
The Process for Granny Flat Exemptions:
Confirm that your Mod is under 60 m² and meets the exemption criteria.
Submit an exemption application to your local council with basic details (e.g., plans, specifications).
Receive council approval and proceed with the installation.
This legislation is expected to significantly streamline the setup of smaller Mountain Mods, particularly for families looking to add extra space for relatives or rental purposes.
-
Resource consent ensures your Mod aligns with local planning rules. You'll need this if:
The Mod breaches local zoning rules (e.g., building too close to a boundary).
The property is in a sensitive area (e.g., near a lake or protected landscape).
You're adding additional dwellings to a property that exceed council density rules.
Examples of When Resource Consent Is Required:
Placing a Mod on rural land in a protected landscape.
Installing a Mod in an area with strict height or setback rules that your Mod breaches.
Examples of When Resource Consent Is NOT Required:
Placing a Mod on urban land where zoning allows for additional dwellings.
Installing a compliant Mod that meets all district plan rules (e.g., setbacks, height, and density)
-
A Code of Compliance Certificate confirms that your Mod has been built in accordance with the approved building consent and complies with the Building Code. You need a CCC if:
You obtained building consent for your Mod.
The Mod is intended as a permanent dwelling or connected to utilities.
When CCC Is Required:
Installing a Mod as a permanent home or granny flat.
Connecting the Mod to sewerage, water, and power systems.
When CCC Is NOT Required:
Using the Mod as a temporary or non-habitable structure (e.g., a storage unit).
Installing a Mod under the new granny flat exemptions (though compliance with the Building Code is still mandatory).
To apply for a CCC, you must submit relevant documents to the council after completing construction, including inspection records and any compliance certificates for plumbing or electrical work.
-
Where you place your Mod matters. Some areas, like Queenstown and Wanaka, have stricter rules due to environmental sensitivity. In rural areas, rules may be more relaxed. Always check the local council's requirements for your property's location.
-
Building Consent: Standard applications take 20 working days. For exempt granny flats, it's quicker.
Resource Consent: Timelines vary but expect 20-40 working days for standard applications.
Code of Compliance Certificate: Typically issued within 20 working days of application, provided all requirements are met.
To avoid delays, make sure your application is complete and includes all required plans and documents